Project Dates

Tab Project dates is separated into 2 columns and 3 sections

Section 1

  • Left column contains phase specific data (Strategy, Acquisition, Booked)

    Strategy
    • Start of Strategy - system generated date, cannot be changed

    • Expected start of acquisition date (mandatory)
      If project is linked to market then default date is set about 30-36 months before SOP, can be changed by user)

    • Expected Award of Business (mandatory)
      If project is linked to market then default date is set about 24-36 months before SOP (but always after Expected Start of Acquisition)

    --> Dates are required for Strategic and Acquisition reporting

    Acquisition

    Additional entries are required:

    • Customer RFQ details if available

    • Planned Evaluation Team Kick Off Date (optional)

    • Calculation Due Date (optional)

    • Quote Due date (mandatory)

    • Expected Award of Business date (mandatory)

    Start of Acquisition date is system generated and cannot be changed

    Booked

    Editable Award of Business date (impact on Order intake Report)

  • Middle column - planning based dates (see in picture)

    • SOVP (Start of Volume Planning), default 24 months before SOP

    • SOP (Start of Production (selected model(s))

    • EOP (End of Production (selected model(s))

    • EOVP (End of Volume Planning), default 60 months after EOP

Section 2

  • Additional project specific milestones, set by user (optional)

Section 3

  • Additional Project Dates attributes (if required), defined in DA-settings