Project Dates
Tab Project dates is separated into 2 columns and 3 sections
Section 1
Left column contains phase specific data (Strategy, Acquisition, Booked)
Strategy
Start of Strategy - system generated date, cannot be changed
Expected start of acquisition date (mandatory)
If project is linked to market then default date is set about 30-36 months before SOP, can be changed by user)
Expected Award of Business (mandatory)
If project is linked to market then default date is set about 24-36 months before SOP (but always after Expected Start of Acquisition)
--> Dates are required for Strategic and Acquisition reporting
Acquisition
Additional entries are required:
Customer RFQ details if available
Planned Evaluation Team Kick Off Date (optional)
Calculation Due Date (optional)
Quote Due date (mandatory)
Expected Award of Business date (mandatory)
Start of Acquisition date is system generated and cannot be changed
Booked
Editable Award of Business date (impact on Order intake Report)
Middle column - planning based dates (see in picture)
SOVP (Start of Volume Planning), default 24 months before SOP
SOP (Start of Production (selected model(s))
EOP (End of Production (selected model(s))
EOVP (End of Volume Planning), default 60 months after EOP
Section 2
Additional project specific milestones, set by user (optional)
Section 3
Additional Project Dates attributes (if required), defined in DA-settings